Timeline

DOE Senior Project

2019

Applied a Design of Experiments methodology to optimize a bio-culture bottling line, targeting torque inconsistencies in the capping process responsible for an estimated $617,000 in annual leakage costs for the project sponsor.

A screening DOE identified three improvement paths — friction disk wear reduction, optimized machine settings, and induction sealing. Economic analysis concluded that optimized settings offered the lowest implementation threshold, with induction sealing recommended as a long-term addition.

Senior Project Poster — Characterization of Bottle Torquing Process
Senior project shareout poster — Cal Poly IME 481, 2019
Bottling line screen recording — process demonstration, Feb 2019
A few of the main machine settings and torque readout monitor
Leak testing equipment